SpaceX Starmind Gets FCC Approval: What 1 Million Satellites by 2040 Would Take

The FCC's deadlines would require up to 684 Starmind satellites entering service every day by the late 2030s, and four of the six orbit shells can't be used until SpaceX files a final debris plan.

By SpaceTracker.live TeamPublished 8 min read
Artist's impression of a large solar-winged data-center satellite orbiting above Earth's night side, with similar satellites in the distance
Artist's impression: AI illustration made with Google Gemini, edited by SpaceTracker.live Team. Not an actual photo.

SpaceX Starmind, the company's planned network of solar-powered data-center satellites, now has a US licence for up to 1,000,000 spacecraft. The Federal Communications Commission granted it on 25 November 2026. That one number is roughly 58 times the active satellites in orbit today, and the FCC has also set a deadline schedule that runs to 2040. This article looks at what the approval actually covers and what those deadlines would demand in practice.

The FCC's news release calls it the first authorization in US history for a constellation of data centers in space. FCC Chairman Brendan Carr framed it in national terms: "America is leading the world into the era of super intelligence."

What the FCC approved for SpaceX Starmind

The legal document is a 25 November order signed by Courtney Reinhard, chief of the FCC's Space Bureau. It grants part of SpaceX's application, with conditions, and defers the rest. SpaceX filed that application on 30 January 2026, and the FCC opened it for public comment on 4 February.

The FCC licenses radio, not computers. So the core permission is narrow: Starmind satellites may use two Ka-band frequency ranges for backup and emergency telemetry, tracking and command. Normal traffic is meant to travel by laser, through optical links between the satellites and SpaceX's Starlink network. The radio bands are only a fallback if those links fail, and SpaceX may not cause interference to anyone else using them.

The order rejected petitions to deny the application from three opponents: Viasat, Amazon's Amazon Leo broadband project (filed as Kuiper Systems), and the American Astronomical Society (AAS). Many public comments worried about crowding orbit with a million satellites. The Space Bureau answered that its rules set no limit on satellite numbers and that it "declines to invent a de facto rule" in a single licensing case.

Where the satellites would fly, and the 600 km catch

According to the FCC order, Starmind is licensed for altitudes between 500 and 1,002 km. SpaceX's original request reached up to 2,000 km. The order lists six operating shells, each a narrow band of altitude:

  • 550–568 km, inclined 26–32°
  • 565–585 km, sun-synchronous (97.7°)
  • 686–718 km, inclined 30°
  • 707–744 km, sun-synchronous (97.2°)
  • 946–978 km, inclined 30°
  • 967–1,002 km, sun-synchronous (99.4°)

Here is the detail most headlines skipped. Only the first two shells sit below 600 km. The FCC accepted SpaceX's debris plan for satellites below that height, but before any Starmind satellite goes higher, SpaceX must file a modification with a final orbital debris plan. The FCC also deferred SpaceX's request to dispose of higher satellites in other orbits, including orbits around the Sun, instead of bringing them down through the atmosphere. In practice, four of the six shells cannot be used yet.

Height matters because it sets how long dead hardware lingers. At 550 km, a satellite circles Earth in about 95.6 minutes, roughly 15 times a day, and air drag slowly pulls failed objects down. At 1,002 km, one orbit takes about 105.2 minutes and drag is far weaker, so anything that fails there can stay up much longer. You can check both figures with our orbital period calculator by entering the altitude.

The deadlines, counted in satellites per day

The licence is not open-ended. Under the order, it becomes void if SpaceX misses any of these dates:

  • 25 November 2033: at least one satellite in its assigned orbit and operating
  • 25 November 2035: 10% of the maximum, or 100,000 satellites
  • 25 November 2038: 50%, or 500,000 satellites
  • 25 November 2040: the full constellation

Divide each step by the days between deadlines and the scale becomes clearer. Going from 1 to 100,000 satellites in 730 days means about 137 new satellites in service every day. Going from 100,000 to 500,000 in 1,096 days means about 365 a day. The final step, 500,000 more in 731 days, works out to about 684 a day.

SpaceX Starmind deployment deadlines compared with all active satellites today Horizontal bars on one linear scale. All active satellites today: 17,247. Starmind FCC deadlines: 1 satellite by November 2033, 100,000 by November 2035, 500,000 by November 2038 and 1,000,000 by November 2040. The required pace is about 137, 365 and 684 satellites a day between deadlines. SpaceX Starmind: what the FCC deadlines require Satellites that must be in orbit and operating, on one scale with today's whole active fleet All active satellites Nov 2026, every operator 17,247 Deadline 1 25 Nov 2033 1 satellite Deadline 2 25 Nov 2035 · 10% 100,000 ≈137 a day from 2033 Deadline 3 25 Nov 2038 · 50% 500,000 ≈365 a day Deadline 4 25 Nov 2040 · 100% 1,000,000 · ≈684 a day 0 250k 500k 750k 1M Pace = extra satellites needed ÷ days between deadlines, if spread evenly. Ignores failed satellites that would need replacing. Sources: FCC order DA 26-1273 (25 Nov 2026); active count from Jonathan McDowell (18 Nov 2026). Graphic: SpaceTracker.live
On a single scale, every working satellite in orbit today is a sliver next to the 2040 Starmind target. Graphic: SpaceTracker.live

These figures count satellites that must be operating, not launches. Any satellite that fails would need a replacement, so the real number built and flown would be higher. For comparison, SpaceX has about 11,200 Starlink satellites in orbit after more than seven years of launches. At the 684-a-day pace of the final stretch, SpaceX would match that whole fleet in about 16 days.

SpaceX's own plans run earlier than the FCC's minimums. Spaceflight Now reports that Elon Musk expects the first launch in the third quarter of 2027, on Starship, with volume building through 2028 and 2029. Those are company forecasts, not part of the licence. Starship is still early in its orbital flight history, and the SpaceX launch schedule will show when Starmind hardware actually starts flying.

How big a SpaceX Starmind satellite would be

These are not small spacecraft. Spaceflight Now, citing SpaceX's Michael Nicholls, puts each satellite at about 75 m across its wings and 30 m tall once deployed, with roughly 250 kW of power, about one rack of computer hardware. For scale, the International Space Station is about 109 m across. Each Starmind satellite would be a large fraction of that, and the plan calls for up to a million of them.

Size is the root of the astronomy concern. A bigger surface reflects more sunlight, so it can look brighter from the ground. Starlink satellites are already easy to spot shortly after dusk; our Starlink pass finder shows when they can be seen from your location. How bright Starmind satellites will actually look has not been measured, because none has flown yet.

Why astronomers objected, and what the FCC said it cannot regulate

The AAS has long warned about the combined effect of many bright, reflective satellites on optical and infrared astronomy and on the natural night sky. Responding to the decision, the society said it was "disheartened and dismayed," according to its 25 November statement.

The order answered the astronomy concerns in three steps:

  • Visible-light astronomy: no extra conditions. The FCC pointed to SpaceX's commitment to coordinate with the National Science Foundation, and said the grant was coordinated with NASA, NOAA and federal astronomy groups.
  • Infrared astronomy: the AAS argued that waste heat from a million computing satellites could raise the infrared glow of the sky. The FCC said this falls outside the radio operations it licenses.
  • Environment and atmosphere: no further environmental review. The FCC pointed to its October 2026 finding that licensed operations in space take place outside US territory, so its environmental review law does not apply to them.

That leaves a gap worth understanding. The FCC regulates radio signals and, through them, debris rules. Its rules do not cover the protection of optical astronomy, and the order says so plainly. So there is no FCC brightness limit for these satellites. Any brightness mitigation for Starmind will depend on what SpaceX chooses to do and agrees with the NSF.

What happens next

SpaceX has 30 days from 25 November to decline the grant as conditioned. If it does nothing, the conditions count as accepted. From then on, it must file reports by 1 January and 1 July each year covering close approaches with other objects, satellites removed from service, re-entries and the number deployed. The 15-year licence term starts only when SpaceX certifies that its first Starmind satellite is in orbit and working.

The bigger open item is the 600 km limit. Until SpaceX files a final debris plan and the FCC approves it, the four higher shells stay off-limits. SpaceX is not alone, either. The FCC said it is reviewing other orbital data center proposals, and Google's Project Suncatcher already has a launch booked for 2029.

For now, the sky looks the same. No Starmind satellite has launched, and the count of active satellites still sits near the 17,200 explained in our guide to how many satellites are in orbit. The next real milestone is SpaceX's debris filing for the higher shells. After that comes the first launch, the first time anyone can measure how bright a Starmind satellite really is.